Bourne Westfield Primary Academy, Lincolnshire
Our installation team have removed chain-link fencing for Bourne Westfield Primary and installed 2.0 mtr high Safeguard mesh fencing.
This project involved the following works:
Take down 171m of existing chain-link fencing and gates and dispose of in accordance with local regulations.
Supply and install 165m of 2m high green Defender V mesh fencing
Supply and install 1no 1200mm wide single leaf pedestrian access gate
Supply and install 1no 4000mm wide double leaf vehicle access gate